REMOVAL AND INSTALLATION



Pre-removal and Post-installation Operation
  • Engine Coolant Draining and Refilling (Refer to GROUP 14 - On-vehicle Service, Engine Coolant Replacement ).
  • Battery Removal and Installation.





Removal steps


1.
Engine cover


2.
Battery cable clamp


3.
Engine oil level gauge and guide assembly


4.
O-ring


5.
Transmission fluid level gauge and guide assembly


6.
O-ring


7.
EGR valve connector


8.
EGR valve

>>B<<
9.
EGR valve gasket


10.
EGR pipe gasket


11.
EGR pipe B


12.
EGR pipe gasket


13.
EGR pipe heat protector


14.
EGR pipe A

>>A<<
15.
EGR pipe gasket


16.
EGR pipe gasket


17.
Water hose


18.
Heater piping hose connection


19.
EGR cooler


20.
EGR cooler bracket

INSTALLATION SERVICE POINTS



>>A<< EGR PIPE GASKET INSTALLATION



The projection on the EGR pipe gasket should be position as shown.

>>B<< EGR VALVE GASKET INSTALLATION



The projection on the EGR valve gasket should be position as shown.