REMOVAL AND INSTALLATION







Removal steps


1.
Propeller shaft assembly (Refer to GROUP 25 - Propeller Shaft ).


2.
Cover


3.
Breather hose connection


4.
Connector connection


5.
Bracket

>>A<<
6.
Electronic control coupling


7.
Wave washer

INSTALLATION SERVICE POINT



>>A<< ELECTRONIC CONTROL COUPLING INSTALLATION



1.Check that the length of the electronic control coupling stud bolt (A) is within the standard value range.
Standard value: 21.6 - 24.4 mm
2.If it exceeds either of the limits, clean the threads for the electronic control coupling and replace the stud bolt.
Tightening torque: 13 ± 2 N·m